IBM Covered Walkway & Carpark
Value: €425,510.00
Client: IBM International – Contact Paul Lynch 087 9262148
Click images above to view larger.
Brief Summary Works:
The above works were carried out for IBM International, which is one of Ireland’s leading providers of advanced information technology, products, services and business consulting expertise. RCCS Ltd pre – qualified thru a rigorous pre-qualification process where all aspects of our companies procedures were assessed from our Health and Safety record, quality control, environmental record, corporate responsibility and previous works carried out. From being successful in getting on the selected tendering list, we then proceeded in pricing the above works and were awarded the 6-month contract.
Scope – A brief summary of the works consisted of:
- Upgrading existing drainage with new 750mm Diam Concrete Pipes, to facilitate a attenuation system. Extensive existing services in the location including fibre optic cables, and high pressure gas mains, and ESB therefore careful digging and safe operations during all works was paramount throughout the project
- GPR survey carried out for full site
- Klargester Bypass Separators and Flow Controls fitted
- New Carpark Construction and Lining
- New Street Lighting
- Metal Walkway Main structure – 100 SHS 8.0mm (C1) columns at 3.0m centers on 250 x 250 x 10mm thick Base Plate on 20mm grout with 4no dia. holes; 100 SHS 8.00mm (B1) beams at 3.0m centers; 100 x 60 RHS 5.0mm (B2) Beams running horizontally to each side of structure. Fitted with curved roof cladding and selected perspex cladding horizontal to sides.
- New ramp construction works throughout the site and Fire Road
- “Sleeping Policeman” crossings
- Retaining Wall Construction
- Decorative Paving and Stainless Steel Metal Work
- Upgrade Works to Existing Electrical infrastructure; LV Power Distribution Cable, Support & Containment Systems, Earthing and Bonding, Site Diversions and Decommission Works
- Landscaping Works